The Lagos State Government on Monday said the ongoing Oshodi transport interchange will be completed within the first quarter of 2019.
Commissioner for works and infrastructure, Adebowale Akinsanya, in a statement on the state of the project, said it was gratifying to report that substantial progress had been made towards its completion.
Mr Akinsanya added that with the ongoing pace of works, the project would be completed within the first quarter of 2019, and operations commencing soon after, saying that commuters around the State should look forward to having a comfortable, accessible and world-class transport system.
Besides, Akinsanya commended motorists and residents in the State for cooperating with government in the implementation of the project, just as he assured that all hands were on deck to expedite work and complete it on schedule.
“At the moment, 83 per cent total work progress has been achieved, including completion of piling works on the three terminals and completion of the piling works for the Skywalks.
“Among others, we have also completed works on the pile caps for the three terminals, concrete works of the buildings, ground floor works on all the loading bays for the three terminals, erection of steelworks for the skywalks and terminals and taxi park and car park area, while roadworks around the terminal are at an advanced stage as well as bus holding bays around the terminals also at an advanced stage,” Akinsanya said.